November 12, 2026
At about 5 p.m. on March 26, 2025, a southbound driver on State Road A1A in Manalapan needed more than six minutes to get through one construction zone. That was after crews had already retimed the signals to favor southbound traffic. The Coastal Star photographed the wait and ran the photo with its report on what was under the road. Two private homeowners were building tunnels side by side beneath South Ocean Boulevard.
Many Manalapan lots run from the Intracoastal Waterway to the ocean, and some of them come with a passage beneath the road. These tunnels let owners walk from the main house on the west side of A1A to the beach and a beach house on the east side without crossing the road. Each tunnel is private. Building one shuts down part of the only road through town, and since 2025 the town has decided when that can happen. The state has kept upsetting that schedule.
The two tunnels in spring 2025 were at 1890 and 1900 S. Ocean Blvd. The owners had permits approved in July, and the town attorney told commissioners the town had no authority to stop a valid permit. The tunnels were originally supposed to be finished in November. FDOT permitting ran late, and the town then asked the owners to hold off so the work wouldn't snarl traffic around Thanksgiving and Christmas. That pushed construction into late February and March, the busiest part of the season. In late March, Town Manager Eric Marmer told commissioners the work wasn't expected to wrap up until the middle of May.
The method had also changed. In the past, crews usually closed the two-lane road for about a week and worked almost around the clock. For these two tunnels, the state required the owners to build a temporary "bypass road" on their own property so one lane of traffic could keep moving. Commissioner Cindy McMackin compared the timelines at that meeting, as the Coastal Star reported:
| How the road is handled | Time on A1A, per Commissioner McMackin |
|---|---|
| Full road closure | About five days |
| Half the road at a time | About two weeks |
| Bypass lane on the owner's property | Six weeks or longer |
The older approach shows up in a 2020 notice from The Coastal Star. Tunnel work at 1940 S. Ocean Blvd. was expected to close A1A from Monday, Sept. 14, through Friday, Sept. 18. That was one week, scheduled well before season.
The bypass method keeps traffic moving, but it stretches the disruption over weeks. In 2025 it also exposed a signal problem. The portable signals gave northbound and southbound traffic equal time no matter how long each line was. Commissioner Dwight Kulwin described it as "almost always a one-way problem," with 10 cars heading north and 125 heading south. Marmer also told commissioners that at least three or four more tunnels were being planned.
On May 20, 2025, the Town Commission adopted Ordinance No. 395, which updates the town's rules for underground pedestrian passageways beneath South Ocean Boulevard. The town posts a business impact estimate for the ordinance. Its tunnel application checklist states the seasonal rule. Construction, repair or maintenance of these passageways "shall not commence or be carried out between November 1 and April 14 of the following calendar year without express, advance approval from the Town Commission." The commission grants that approval only when the property owner shows good cause, and it considers the effect on neighboring properties and traffic.
The rest of the checklist addresses the 2025 complaints directly, including traffic management and dune protection.
The first request to work past the deadline reached the commission this fall. It came from 1860 S. Ocean Blvd., where the passageway will connect a main house west of A1A with a beach house to the east. The commission first approved that tunnel on May 20, 2025, the same night it adopted the ordinance.
The approved project then waited on the state. RWB Construction Management wrote to the town on Sept. 3, 2026, that FDOT did not issue its approval until Aug. 24, 2026, after a three-year permitting process. "The controlling factor in this schedule has been the Florida Department of Transportation permitting process," the letter said. "Installation could not lawfully commence prior to that issuance." RWB asked to keep working through Nov. 14 and committed to an approved traffic plan and a right-of-way kept "secured and passable."
Commissioners approved the request at their Sept. 8 meeting, the Coastal Star reported. While the work is underway, traffic uses a temporary bypass lane, and a police officer is on site every day and can take manual control of the traffic signal.
Late FDOT permits pushed the 2025 tunnels toward winter, and they did the same to this one. The bypass-lane method then makes every late start last weeks longer.
The town code allows one tunnel per property, and Manalapan's largest estate already has more. The Coastal Star's July 2026 report says the former Ziff estate at 2000 S. Ocean Blvd. had three air-conditioned pedestrian tunnels under A1A when Oracle co-founder Larry Ellison bought it in 2022, and he was allowed to keep all three. The part of the lot to the north that he agreed to buy has a tunnel of its own. On July 14, commissioners agreed he could keep that one too, which brings the estate to four passageways under the road.
Counting only tunnels named in local news, at least eight passageways have been built or approved beneath this stretch of A1A: 1940, 1890, 1900, the four at Ellison's estate, and 1860. The seasonal limit governs when crews may work under the road, and the in-season exception for 1860 is the first time the town has tested it.
Tunnel work isn't the only lane closure on A1A this fall. Just south of Manalapan, Ocean Ridge is replacing a water main along a roughly two-mile stretch of A1A from Corrine Street to Ocean Avenue. The Coastal Star reported that the $1.9 million project is meant to increase water pressure, improve fire protection and replace hydrants on the west side of the road. The contractor is Johnson-Davis, a Lantana-based underground utility company, and contractors told Ocean Ridge commissioners in August that they expected to finish by the end of the year.
FDOT's Palm Beach County traffic report for Nov. 6–13, 2026 lists around-the-clock lane closures on A1A there through late 2026. A temporary signal alternates northbound and southbound traffic through a work zone of about 400 feet, including cars pulling out of driveways and side streets. That week, the zone sat just south of Ocean Avenue with the northbound lane closed. Crews are scheduled Monday through Friday and on Saturdays as needed. The west-side sidewalk and beach access points remain open. Flagging and single-lane closures may also affect Ocean Avenue where it meets A1A.
When commissioners approved the 1860 extension in September, they worried about the tunnel and the Ocean Ridge closures stacking up and backing up weekend traffic. "Then it's like Frogger going down to A1A," Vice Mayor Simone Bonutti said, according to the Coastal Star.
On the town's events calendar, the season doesn't open until the Opening Season Party on Jan. 22, 2027, from 6 to 8 p.m. Before that, a book club meets on Dec. 9 at 4 p.m. at the J. Turner Moore Memorial Library, 1330 Lands End Road.
If you own on the ocean-to-Intracoastal side of A1A, or you're considering a property where a passage under the road matters, Kirsten Smith is glad to talk. Let's Connect.
Her firsthand experience buying, renovating, and investing in real estate provides valuable insight that helps clients make confident, informed decisions at every stage of the process. Contact her today so she can guide you through the buying and selling process.